Class Environmental Assessment Process
The Preliminary Design and Class Environmental Assessment Study followed the Ontario Ministry of Transportation (MTO) Class Environmental Assessment (EA) for Provincial Transportation Facilities (2000). The MTO Class EA provides a decision-making process to make sure that all relevant engineering and environmental factors are considered in the planning and design of transportation facilities. This Detail Design and Class Environmental Assessment Study is continuing to follow the 2000 MTO Class EA and is being undertaken as a Group ‘B’ project, which includes highway improvements that provide/cause a significant modification in traffic access.
A Design and Construction Report (DCR) has been prepared to document the following:
- The detail design of the Recommended Plan and construction staging plan
- A full description of the consultation program
- Identification of all project approvals, licenses and permits that have been or must be obtained
- Environmental impacts, mitigation, and protection measures that will be implemented
- Commitments to future work
The DCR is available for a 30 day comment period, ending October 26, 2026, to provide the opportunity for stakeholders to review and comment on the document. The DCR is available on the project website under the Documentation section of this website. The DCR is also available for in-person review at Bloomfield Public Library (300 Main Street, Bloomfield Ontario) and Picton Public Library (208 Main Street, Picton Ontario).